Earned Value Analysis

Venkataramiah S Annapragada
24/12/2018 0 0

It Compares Performance Measurement Baseline to the actual schedule and cost performance. Performance Measurement Baseline integrates Scope Baseline, Schedule Baseline and Cost Baseline.

 

For each work package the following dimensions are calculated :

  • Planned Value [PV]. Work that was planned to have been completed at a given point of time
  • Budget At Completion [BAC]. Total planned value for the project. Also called Cost Baseline
  • Earned Value [EV]. The measure of work performed at a given point of time
  • Actual Cost [AC]. The total cost incurred to complete the work measured in EV

 Percentage Project Complete at a given point of time. Percentage of EV/BAC

0 Dislike
Follow 2

Please Enter a comment

Submit

Other Lessons for You

Risks in Project Management
Project Management Risk Types are Inherent Risks, Residual Risks, Secondary Risks. These are listed here with examples for the detailed understanding. In Project Management, we often encounter Risks,...

MS Project: Copy calendar from one project to another project
Sometimes user may want to use same calendar of existing project in another project. In such case, there is no need to recreate new calendar in second project. This video explains how copy existing calendar from one project to another project.

What Are Your Skills | Resource Management
The human capital, with the exponential growth in population, is immeasurable huge. Today the talent pool is just terrific. Paradoxically, the skill gap persists despite the overwhelming numbers of resource....

Points to be remembered while creating Project schedule in MS Project
Rule 1 : First task should not have predecessors, Last task should not have successors. Rule 2 : Except first and last tasks, every task must have both predecessors and successors. Rule 3 : Project Summary...

Strategy for PMP Preparation
Hello Friends, Hope you are all doing well, positive, focused and energetic to achieve milestones. This time offers us re calibration opportunity of our self where we can write what we need to achieve,...
X

Looking for PMP Training Classes?

The best tutors for PMP Training Classes are on UrbanPro

  • Select the best Tutor
  • Book & Attend a Free Demo
  • Pay and start Learning

Learn PMP Training with the Best Tutors

The best Tutors for PMP Training Classes are on UrbanPro

This website uses cookies

We use cookies to improve user experience. Choose what cookies you allow us to use. You can read more about our Cookie Policy in our Privacy Policy

Accept All
Decline All

UrbanPro.com is India's largest network of most trusted tutors and institutes. Over 55 lakh students rely on UrbanPro.com, to fulfill their learning requirements across 1,000+ categories. Using UrbanPro.com, parents, and students can compare multiple Tutors and Institutes and choose the one that best suits their requirements. More than 7.5 lakh verified Tutors and Institutes are helping millions of students every day and growing their tutoring business on UrbanPro.com. Whether you are looking for a tutor to learn mathematics, a German language trainer to brush up your German language skills or an institute to upgrade your IT skills, we have got the best selection of Tutors and Training Institutes for you. Read more